Project Milestone Definition

  • Contract Complete
    • SW 3rd party contracts
    • terms and conditions
    • Schedule and test plan from 3rd party and vendor
  • Code Complete
    • SW features and functions are implemented
    • No changes on SW architecture
    • QA execute System Test Plan fully
    • The code is not yet robust and stable
  • Visual Freeze
    • UI is fully implemented and not expected to change
  • Test Complete
    • Finish one full pass of the System Test Plan
    • Any System Test Plan blocking issue has been identified and resolved
    • Base ROM must pass Hopper on 10 devices for 10 hours
    • Start LTK on Test Complete ROM
    • TC ROM will be used for IOT,Field trials, PTCRB and GCF test
      • IOT:Interoperability Testing, a test that verify the ability to send/accept information from other component/system/unit
      • PTCRB:A organization funded by operators, and certificate mobile devices for compliance with operators' networks(for GSM only?)
      • GCF:Global Certification Forum which is a partnership between network operators and terminal manufactures that provides an independent programme to ensure global interoperability of 2G and 3G mobile wireless terminals
  • Stabilization Complete
    • LTK has been run on the weekly ROM and no failing tests remain
    • Fully integrated ROM passes Hopper test at 25 hours on 10 devices
    • Stability testing is running and there are no failing tests (performance, interoperability,benchmark)
    • No priority 1 or 2 defects
  • Zero Bug Bounce
    • No active bugs
    • Only blocking bugs are resolved
  • Release Candidate
    • The code has been stabilized with no changes for a period of 5 days
  • Release to Manufacturing
    • Operator TA received
    • NSTL Approval granted